More than three years after a deadly underground gas explosion damaged Lilian Ngoyi Street in the Johannesburg CBD, the city has announced practical completion of the second phase of road repairs, bringing the delayed R192M project closer to the finish. The Johannesburg Roads Agency (JRA) confirmed on Monday that work between Ntemi Piliso and End streets had reached practical completion, although finishing work and street furniture installation remain.
Mayor Dada Morero said the rest would be completed within two weeks. “We are proud to reopen Phase 2,” said Morero. The project has faced several delays, with its deadline moved from August to October this year and in August 2024 the JRA ended its agreement with the original contractor before appointing a replacement. The prolonged closure disrupted taxi operations, forcing drivers onto longer routes and raising fuel costs. South African National Taxi Council Johannesburg spokesperson Sabata Mbobo welcomed the reopening, saying it should ease congestion and improve movement through the CBD, after operators struggled to reach their usual routes and connections. The diversions also delayed commuters connecting to Rea Vaya and Gautrain stations.
For informal traders, completion offers little relief. South African Informal Traders Forum representative Brain Phallo said traders had been told the street would no longer accommodate informal trading, even though some hold smart cards authorising them to trade, because it has been declared a non trading street. The organisation is challenging the decision, arguing that the city did not follow the required procedures and is awaiting a court judgment. Phallo said the city’s Department of Economic Development indicated there were no plans to demarcate or allocate trading spaces on the street, that traders lost customers and income during construction and that Johannesburg Metropolitan Police Department officers had been chasing them away. Traders, he said, were only formally told last week and the city has made no provision for their return or for alternative spaces.
The repairs followed the explosion on 19 July 2023 on the street, formerly known as Bree Street, which killed one person, injured several others and damaged vehicles and underground infrastructure. Phase 1, between Harrison and Kruis streets, was finished in August 2025 and opened the following month and included rebuilding the underground tunnel, replacing damaged water, sewer and stormwater infrastructure and installing gas detection and ventilation systems. Phase 2 reduced traffic lanes from five to three and widened pavements and added stormwater upgrades, trading spaces, bus stops, public toilets and street furniture. Morero said the changes support the city’s transit mall concept and Inner City Transport Master Plan and Transport. MMC Kenny Kunene said the street carries between 1,800 and 2,000 vehicles in peak hours, including minibus taxis.
JRA Chief Executive Zweli Nyathi said construction was complicated by ageing underground services, adverse weather, infrastructure relocation and sinkholes caused by erosion and leaking services and that recovery plans were put in place. The city said more than 200 Expanded Public Works Programme participants were employed and 27 small, medium and micro enterprises took part. Motorists and pedestrians are asked to follow temporary road signs and safety instructions while the outstanding work is completed.